8 January Time Sheets are attachments that document the time or cost of work done for a certain Operation. These can necessary for Operations with a Price Type of ''Running Cost'' or ''Hourly Rate''.
[[File:SC_TSIndicator.png|800px|thumb|none|Timesheet-enabled operations are marked with the above indicator in both the Workorder and Operation views.]]
Time Sheets can be enabled for an Operation:
* During turnaround/shutdown planning by setting the Price Type.
* During execution by clicking the ''Enable Timesheets'' button, found in the Activity Details area of an operation.
** Visibility of this button is limited by user rights.
{{Hint|An overview of all Time Sheets can be viewed in the [[Scope_Changes#Overview_of_Scope_Changes_and_Time_Sheets|Scope Changes]] module in the MaTaP client.}}
== Timesheet-Enabled Work ==
If Time Sheets are enabled, a dedicated tab is added to the Activity Details area where contractors can attached documents to log their work.
[[File:SC_TStab.png|800px]]
A new Timesheet can be added by clicking the ''Add Timesheet'' button.
For each added Timesheet, the contractor must input the '''Cost''' and a brief '''Description''' of their work.
The cost of all attached invoices is tracked as the ''Running Cost'' on that operation.
The documents can be viewed (opens up a relevant external app on the same system), and exported after execution.
==== Budgeting ====
If a budget has been set for a particular operation, the Running Cost is shown in relation to the overall budget, with a bar showing the overall progress.
{{Attention| Attaching a Timesheet that would go over the budget for that particular operation will be rejected (as shown with Declined status above).}}