== Commissioning Tasks ==
There are several kinds of task cells on the Commissioning Wallpaper;
<div class="mw-collapsible mw-collapsed" data-expandtext="Show Image" data-collapsetext="Hide Image" style="width:700px;">
* '''Standard Commissioning Tasks (SCT)''' represent single tasks to be executed overall on the sub-system.
** The cell of one SCT displays the status of the SCT by showing its color;
*** The SCT status can be set and changed using the four indicators.
*** The "Navigate To Turnaround Wallpaper" option opens the Turnaround Wallpaper and applies a filter based on the sub-system of the original SCT.
<div class="mw-collapsible-content">
[[File:CommissioningTaskStandardBlured.png|500px]]
</div></div>
<br>
<div class="mw-collapsible mw-collapsed" data-expandtext="Show Image" data-collapsetext="Hide Image" style="width:700px;">
* '''Grouped Commissioning Tasks (GCT)''' represent a group of normal Operations collected under the same sub-system.
** The cell of one GCT displays the status of the GCT by showing its color.
*** On a GCT, the only option for changing status is to set ''Complete''. In this case all unfinished Operations belonging to this GCT will be set to finished (100%) and a history entry will be created for the GCT. This option is only available if the status of the GCT is ''Not Started'' or ''Ongoing''. All other status can't be set.
*** The "Navigate To Turnaround Wallpaper" option opens the Turnaround Wallpaper and applies a filter based on the sub-system of the original SCT.
<div class="mw-collapsible-content">
[[File:CommissioningTask.png|500px]]
</div></div>
<br>
[[File:CWP_CommissioningTasksWithPopup.png]]
<br>
In the above example, we see several different examples of SCTs and GCTs, which can be differentiated by the second line (SCT: "-" or date, GCT: finished / total operations).
tbd: Status x date
tbd: Popup --> operations
 
 
* '''Punchpoint Commissioning Tasks (PCT)''' give an overview of the number of completed [[Punchpoints]] of each Priority type (A to D).
** The cell of each Punchpoint column displays the status of the ''highest priority active punchpoint'' by showing its color.
<br>
[[File:CWP_PunchpointTask.png]]
<br>In this the above example, we see that this particular sub-system has 6 punchpoints in total (from the punchpoint indicator on the Commissioning Workpackage or ''CWO''), with the highest being of priority A. <br>We can verify this in the A column, where 1 of 2 punchpoints is still active. <br>The B and D columns show that there are respectively 2 and 1 punchpoints of that kind, and all 3 are still active. However, from the green status color for the C cell, we can see that all punchpoints of this priority are cleared, and we can verify that 0 punchpoints are active, of a total of 1.