= Key Features =
'''Advanced Visualization''': The Commissioning Wallpaper displays Commissioning Workpackages and Commissioning Tasks. The Commissioning Workpackages are linked to their respective WorkOrders on the Turnaround Wallpaper, and the Commissioning Tasks are, in turn, linked to all their associated Operations.
'''Interactive Grid Layout''': Users can navigate through project data via a scrollable grid. This grid includes fixed row headers that are each a Commissioning Workpackage and column headers that are each an Commissioning Code. Commissioning Tasks are categorize according to their Commissioning Workpackage and Commissioning Code.
= Detailed Visualization =
'''Color-Coded Commissioning Task Tiles''': Each commissioning task tile is color-coded based on its status to provide quick visual cues about the progress of operations. Only the operations that are assigned to the respective commissioning task are considered:
* WHITE: "Not started"
** Not a single operation has its progress status set to N/A or within the 0-100 range.
* GREEN: "Complete"
**All operations have a progress status of either N/A or 100.
* YELLOW: "On Going"
** At least one of the operations has a progress status set to N/A or within the 0-100 range.
* DARK GRAY: "Not Applicable"
** The commissioning task itself is not applicable.
= Commissioning Task =
When a left-click is made on a commissioning task, a detailed window appears, displaying the following information:
* Commissioning Code
* Responsible Company
* Status of the Commissioning Task
* History of the change status of the Commissioning Task
[[File:CommissioningTask.png|500px]]
When the status of the commissioning task is changed in this window, all status of the associated operations are also updated.