Changes

Scope Changes

198 bytes added, 20 January
/* Overview of Scope Changes and Time Sheets */ fixed broken link
==== Price Details ====
* '''Price Type''' indicates whether the Scope Change shall be billed on a ''Fix Price'', ''Unit Rate'', or ''Hourly'' basis.
** Operations with a Unit Rate or Hourly price type require the attaching of [[Time_Sheets]] for budgetary tracking.
* The '''Estimated Cost''' gives an indication of how much the work should cost overall.
* The '''Early Start''' date is copied over from the Workorder. It represents the earliest that work can begin on an operation and cannot be altered.
All of the above details, aside from the unique Scope Change Number and Early Start, can be altered given the correct user rights.
However, these properties become fixed and can no longer be edited once the Scope Change has reached ''Financial Approval'' status.
[[Category:MaTaP|Scope Changes]][[Category:MaTaP UWP|Scope Changes]]
== Approval Workflow for Scope Changes ==
* '''Clarification meeting''' needed / resolved.
* '''Tag''' / '''Workorder''' / '''Scope Change Numbers''', and '''Scope Change Description''' below.
* '''Status''' if it is a Scope Change, or '''[[Time Sheets|Time Sheet]]''' indicator if it is not.
** Possible statuses are Created, Issued, Technically Approved / Declined, Financially Approved / Declined.
* '''Activity Number''' and '''Description''', and '''Responsible''' company below.